Harris Medical Centre Extension

From December onwards there will be limited parking available at the Harris Medical Centre. This is due to the following building works taking place which are estimated to be complete within 6 months.

Plans and Elevations

Site Plan

Ground Floor Plan

First Floor Plan

Whilst this will cause some disruption the building works will add 3 more consulting rooms to the ground floor, a further consultation room upstairs and extended meeting and training facilities.

Due to the large amount of new housing projects in Mereside and the surrounding areas we felt it wise to extend the site so as to future-proof the surgery for the growing local population.

Progress Updates

Site visit – 1st December

Progression of site set up including existing car park amendments and foundation dig.

Site Visit – 15th December

Piling works have been completed. Ground beam reinforcement and shuttering progressing ready for concrete pour due week